Well more delays.... just the norm really.
The sewer was inspected last week but the water connection was finished after the sewer inspector had left ,and now water needs to be inspected separately.
So..... water inspection booked in for Thursday, which means frames can't arrive until water is buried which is after inspection. So frames have been rebooked for Friday.
Confused yet?
The good news is that our chippy is busy assembling the frame for the other job our builder is doing in the next street and they should be finished when our frame is due to arrive.
So maybe the frame will start on Friday but more than likely next week instead.
Hi Andy, i hope you can get your frames up soon :) We have had rain delays here so i hope that helps you catch up! :)